Budlong provided engineering services to USC Medical Facility. USC required to have the generator day tank relocated. The current generator and fuel system were designed by a previous consultant. The drawings were approved by OSHPD, installed and inspected. Nevertheless, the project had not been closed-out due to a new inspector requesting the day tank to be relocated.The tasks provided are listed as follows:
  • • Design new day tank and piping relocation. Vapor tank relocation. Existing underground fuel tank to remain.
  • • Prepared OSHPD submittals
  • • Provided construction meetings and construction administration services.

Project Type: Healthcare

Location: Los Angeles, California

Client:USC

Cost$18M