Sunniva Facility
Budlong provided a preliminary study and MEP Design for this 130,000 SF facility.
- The existing plant (chillers and a cooling tower) was designed to provide 2,800 tons of cooling.
- There was no permanent emergency power.
- There was a boiler plant serving the needs of the full facility.
- 4100 tons of cooling
- 10 megawatts of emergency power.
- Integrate a RO system currently in the design-build stage
Project Type:Industrial & Labs
Location:Los Angeles, California
Year: 2010 - 2012
Client: LAWA
Cost: $25M
Size: 58,000 sf