Projects

Proctor & Gamble
Tenant Improvements and Water Feature Renovation
Project TypeCommercial
LocationOxnard, California
Year2010-2012
ClientProctor & Gamble
Cost$.10M
Size6,000 sf

Project Details

Budlong provided demolition plans to remove existing offices from 60″x100′ ground floor location in building 1#10 at Procter and Gamble’s Oxnard, CA plant. The new space included (8) team rooms (180 sqft each), with overhead projectors, motorized screens, glass fronts, work boards, and central conference table for 6-10 people, Library space with (4) large conference tables to accommodate 60 people, (4) traditional executive offices with (1) small conference room. Open work group space (41×60) with (11) four- person workstations, (1) single person work station and printer/copier/fax/vending area.